Approval record: Design input
Freeze the simultaneous heat loads that define everyday duty and any overlapping changeover loads. Name supply and return temperatures, fluid composition, quantity, destination, three-phase supply, connected load, footprint and whether the RFQ is a refrigeration package or a loop with pumps, reservoir and distribution-loop controls. If hydrogen duty is in the project, record that isolation, materials compatibility, leak response and installation classification stay with the project engineer and a specialist supplier.
Supplier answer
Each bidder should split industrial process cooling system price into refrigeration package, pumps, reservoir, loop controls, freight, installation, training and spare parts. Ask who supplies pumps, reservoir and distribution-loop controls. Attach the selection at the stated fluid temperatures, the connected load in kW at the stated supply frequency, and any temperature-stability limits at low load or extreme ambient. FAT and SAT should reuse the same load schedule.